Unanchored, Anchored and Blocked Activities

Please note: The behaviour described in this section refers to Activities with an Activity Status of Scheduled, Current or Completed only.

Unanchored Activities will move automatically if a change is made that affects the period where the Unanchored Activity is placed. This Activity will move in accordance with the following rules:

Anchored and Blocked Activities do not move automatically.  The difference between an Anchored Activity and a Blocked Activity is for a Blocked Activity any Unanchored Activities after the finish time of this Activity do not automatically move to an earlier time if there is space available to do so.

For Anchored and Blocked Activities that are divided into a series of parts, only the Start of the whole Activity (that is, the Start of the first part) is locked.  All other Activity parts behave as if they are Unanchored.